RENOVA, Inc.
Notice of Resumption of Operations at Tokushima Tsuda Biomass Power Plant
Notification regarding the resumption of operations at Tokushima Tsuda Biomass Power Plant. The repair of the high-pressure turbine's steam control valve damage has been completed, and normal operations resumed on July 25, 2026.
Key Figures
- Operation suspension period: 17 days (from July 8, 2026, to July 25, 2026)
- Repair completion date: July 25, 2026
- Repair start date: July 8, 2026
AI要約
Overview of Resumption of Operations
Revor Corporation announced the resumption of operations at the Tokushima Tsuda Biomass Power Plant. The repairs related to damage to the high-pressure turbine's steam control valve were completed on July 25, 2026, and normal operations resumed on the same day. The repairs were carried out from July 8, 2026, and the initial period of operation suspension was approximately 17 days. There are no anticipated disruptions to future operations, and stable electricity supply is expected to continue.
Future Outlook and Impact
With the completion of repairs, the impact of power supply disruptions caused by the temporary shutdown of the power plant has been alleviated. Revor emphasizes maintaining safety and stability by continuing routine inspections and maintenance of equipment. The specific repair costs and expenses have not been disclosed; however, the resumption of operations is expected to have a limited impact on future earnings.
Revor Corporation
Company overview · Stock price · Financial data · All IR