kaihan co.,Ltd.
Notice of Commencement of Battery Storage Business and Acquisition of Fixed Assets (Change of Acquisition Target Project)
The acquisition target battery facility has been replaced from KTD-19 to SOIT-31. Location and specifications are of comparable scale, and the contractual price remains the same at 612,600,000 yen, with an outstanding unpaid amount of 208,000,000 yen. Future start of operations will follow the revised schedule, and the impact on consolidated results is undetermined.
Key Figures
- Battery facility name: SOIT-31 battery facility, Total contract price: 612,600,000 yen (same amount before/after tax)
- Amount paid: 404,600,000 yen, Unpaid amount: 208,000,000 yen
- Contract amount before replacement: 612,600,000 yen (same as initially disclosed)
AI要約
Overview of Project Replacement
kaihan co.,Ltd. has changed the acquisition target project announced on June 24, 2025, for the battery storage business to the SOIT-31 battery facility based on a memorandum with TOFU LLC. The reason is that additional time is required to obtain understanding from nearby residents. The details after replacement are as follows: SOIT-31 battery facility, location includes Tashirocho and others, Satsumasendai City, Kagoshima Prefecture; specifications DC 8,128 kW / AC 1,959.9 kW; contract amount 612,600,000 yen (same amount before and after tax). The amount paid is 404,600,000 yen and the unpaid amount is 208,000,000 yen.
Outlook and Impact
The revised schedule indicates equipment delivery planned for May 2027 (planned) and commencement of operations in June 2028 (planned). Progress will be disclosed based on the revised schedule. If matters arise that should be newly disclosed regarding the timing of acquisition/operation commencement and the impact on consolidated results for the fiscal year ending March 2027, they will be promptly announced.
kaihan co.,Ltd.