Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing
In light of financing delays and flood damage in Nepal, the completion timing for Phase 1 of the Nepal hydropower projects has been revised to TBD. Due to continued delays in securing funding and impacts on on-site construction, completion and commercialization timings may be further changed. Phases 2 and 3 are currently under reconsideration.
Key Figures
- Current planned completion for PJ1–PJ4: TBD
- Phase 1 interim funding: approx. 100 million yen (Surya's share)
- Phase 1 revenue plan: expected to occur in or after the fiscal year ending March 2027 (19 million yen)
AI要約
Review of Project Plan and Background
The completion schedules for Phase 1 (multiple projects) of the Nepal hydropower projects promoted through consolidated subsidiaries have been reset. Delays in financing and flood damage within Nepal have delayed construction progress, prompting a revision of the model to include adjustments to on-site construction schedules and consideration of rights transfers or project termination. Further changes may occur depending on future financing conditions.
Outlook and Impact
Completion schedules for PJ1–PJ4 remain TBD. For projects from Phase 2 onward, policy decisions are being discussed, including consideration of rights transfers or project termination while taking into account impacts on local operators. Revenue plans and commercialization timing are not confirmed at this time and may be further revised depending on financing and construction progress.