Micronics Japan Co., Ltd.
Notice Regarding Capital Investment for Production Capacity Expansion
Capital investment of 24.1 billion yen to be carried out from 2027 to 2028 to expand production capacity for probe cards for memory.
Key Figures
- Total Capital Investment: 24.1 billion yen
- Investment Period: From 2027 to 2028 (2 years)
- Investment Locations: Aomori Plant (571-2 Machii Minamida, Hirakawa City, Aomori Prefecture; 14-1 Shindatenokiwa, Hirakawa City, Aomori Prefecture), Aomori Matsuzaki Plant (41-1 Matsuzaki Nishida, Hirakawa City, Aomori Prefecture)
AI要約
Overview of Capital Investment
The Company has decided to make focused capital investments in the new building of the Aomori Plant and renovate the production areas of the Aomori Plant and the Aomori Matsuzaki Plant for the purpose of expanding production capacity in response to sharply increasing demand for probe cards for advanced memory semiconductors. The total investment amount is 24.1 billion yen, to be implemented over two years from 2027 to 2028. This is driven by expanded investments in AI data centers accompanying the proliferation of generative AI and increased demand for advanced memory semiconductors.
Future Outlook
This capital investment will not impact the consolidated financial results for the fiscal year ending December 2026. The Company will promptly disclose any material changes in market conditions or performance. The funding is planned to be covered by internal funds and borrowings. Through this, the Company aims to strengthen its presence in the probe card segment for memory and establish a response system for customer demand.