The Hanshin Diesel Works, Ltd.
Notice Regarding Expansion and Capital Investment for the Harima New Assembly Plant
Decide to expand the Harima new assembly plant to increase annual production capacity to approx. 50 units. Investment amount is approx. 18.7 hundred million yen, with operations scheduled to start in May 2028. Funding will be covered by internal funds, and the impact on results is expected to be minimal.
Key Figures
- Planned investment amount: approx. 18.7 hundred million yen
- Production capacity: approx. 50 units per year (approx. 1.7x vs. pre-expansion)
- Scheduled start of operations: May 2028
AI要約
Overview of Business Execution
This announcement concerns the resolution to expand the Harima new assembly plant aimed at optimizing the production system and responding to increased engine demand under the medium- to long-term plan "Go for it! Try it!!" By consolidating large engine assembly functions at the Harima plant, the company will optimize inter-process logistics, improve production efficiency, and strengthen a stable supply system.
Scale of Investment and Impact
The total investment is approx. 18.7 hundred million yen to construct a new assembly plant with a total floor area of approx. 1,531 square meters. Operations are scheduled to begin in May 2028, and post-expansion production capacity will be approx. 50 units per year, about 1.7 times the current level. Funding will be provided from internal funds, and the impact on results for the current fiscal period is expected to be minimal.
The Hanshin Diesel Works, Ltd.