Notice Regarding the Acquisition of Fixed Assets (New Construction at Tohoen Plant (tentative name))
To expand production capacity of the water-based flexo printing processing business, a new plant will be established in Tohoen City. Capital expenditure of about ¥4.3 billion, funded by internal funds and borrowings. Impact on consolidated results for the fiscal year ending March 2027 is expected to be minimal. Construction starts February 2027, completion February 2028, operation scheduled for April 2028.
Key Figures
- Investment planned: approx. 43 hundred million yen
- Plant construction start: February 2027 planned
- Plant completion: February 2028 planned
AI要約
Section Heading
This information concerns the establishment of the Tohoen Plant (tentative name) as a second location to respond to growth in the label-flat market and rising demand for environmentally friendly packaging. The acquired assets include water-based flexo printing machines and related processing equipment, warehouses and logistics facilities, and modifications to existing equipment. Financing is planned to be raised from internal funds and bank borrowings, and the investment includes a new building on approximately 12,000 square meters of site area. The impact on consolidated results for the fiscal year ending March 2027 is expected to be minimal, and subsequent disclosures will be made as appropriate.
Section 2 heading
Looking ahead, the schedule for starting, completing, and commencing operation of the Tohoen Plant is explicitly outlined, confirming that the group’s capacity expansion plan is progressing. The investment is about ¥4.3 billion, with funding planned from internal funds and borrowings. Although the direct impact on performance is expected to be minimal, in the medium to long term the strengthened production framework to meet the growth of the label packaging market may contribute to corporate value.