(Disclosure Item Change)Notice on changes to the progress of Nepal hydropower project by consolidated subsidiaries and the expected monetization timing
Revised monetization timing due to delays in financing for the Nepal hydropower project; adjusted the expected completion of Phase 1. Further disclosures will be made as financing progress warrants. Assumed to be approved at an extraordinary board meeting, and impact on the consolidated results for the year ending September 2027 is being examined.
Key Figures
- Planned completion change (Phase 1): November 2026 → January 2027, 5.5MW/8.3MW/9.1MW/13.7MW at each plant
- Monetization timing assuming financing completed: by September 2026 → currently difficult situation
- Extraordinary General Meeting: to be held in September 2026 (approval assumed)
AI要約
Background and key points of change
This project is the Nepal hydropower project advanced through a consolidated subsidiary, and the monetization timing was published with the assumption of financing completion by September 2026. However, based on current financing progress, it has been determined that financing by September is difficult, and the completion schedule for Phase 1 at each power plant has been changed. Phases 2 and 3 remain unchanged. We will promptly disclose as financing timing/methods are confirmed or if assumptions change.
Outlook and impact going forward
Financing is being negotiated through multiple methods. The revised schedule reflects the minimum timeline assuming financing is completed by November 2026. The impact on the consolidated results for the year ending September 2027 is under review, and any additional information will be disclosed as available. If approval is not obtained at the Extraordinary General Meeting scheduled in September 2026, there is a risk of adopting the usual year-end closing approach; please note this.