{"id":155918,"date":"2026-11-20T18:06:41","date_gmt":"2026-11-20T09:06:41","guid":{"rendered":"https:\/\/japanir.jp\/en\/ir\/3133-20261120-06_wp_disclosure_update\/"},"modified":"2026-11-20T18:06:41","modified_gmt":"2026-11-20T09:06:41","slug":"3133-20261120-06_wp_disclosure_update","status":"publish","type":"ir_release","link":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/","title":{"rendered":"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing"},"content":{"rendered":"<p>In light of financing delays and flood damage in Nepal, the completion timing for Phase 1 of the Nepal hydropower projects has been revised to TBD. Due to continued delays in securing funding and impacts on on-site construction, completion and commercialization timings may be further changed. Phases 2 and 3 are currently under reconsideration.<\/p>\n","protected":false},"comment_status":"open","ping_status":"closed","template":"","meta":{"Ticker":"","DATE":"","longName":"","company_name_ja":"","fullTimeEmployees":0,"address":"","phone":"","website":"","industry":"","sector":"","regularMarketPrice":0,"financialCurrency":"","marketCap":0,"fiftyTwoWeekLow":0,"fiftyTwoWeekHigh":0,"epsTrailingTwelveMonths":0,"epsForward":0,"bookValue":0,"totalRevenue":0,"OperatingIncome":0,"operatingMargins":0,"NetIncome":0,"profitMargins":0,"ebitda":0,"trailingPE":0,"forwardPE":0,"priceToBook":0,"returnOnEquity":0,"recommendationMean":0,"recommendationKey":"","targetMeanPrice":0,"numberOfAnalystOpinions":0,"analyst_earnings_data":"","dividendRate":0,"dividendYield":0,"payoutRatio":0,"totalEsg":0,"environmentScore":0,"socialScore":0,"governanceScore":0,"title":"","providerPublishTime":"","link":"","longBusinessSummary":"","longBusinessSummary_ja":"","quarterly_revenue":0,"quarterly_net_income":0,"quarterly_operating_profit":0,"enterprise_value":0,"price_fetched_at":"","company_officer_1_name":"","company_officer_1_title":"","company_officer_2_name":"","company_officer_2_title":"","company_officer_3_name":"","company_officer_3_title":"","company_officer_4_name":"","company_officer_4_title":"","company_officer_5_name":"","company_officer_5_title":"","company_officers_update_time":"","get_dividend_history_year1":0,"get_dividend_history_year2":0,"get_dividend_history_year3":0,"get_dividend_history_year4":0,"get_dividend_history_year5":0,"get_dividend_history_year6":0,"get_dividend_history_year7":0,"get_dividend_history_year8":0,"get_dividend_history_year9":0,"get_dividend_history_year10":0,"site-sidebar-layout":"default","site-content-layout":"","ast-site-content-layout":"","site-content-style":"default","site-sidebar-style":"default","ast-global-header-display":"","ast-banner-title-visibility":"","ast-main-header-display":"","ast-hfb-above-header-display":"","ast-hfb-below-header-display":"","ast-hfb-mobile-header-display":"","site-post-title":"","ast-breadcrumbs-content":"","ast-featured-img":"","footer-sml-layout":"","theme-transparent-header-meta":"","adv-header-id-meta":"","stick-header-meta":"","header-above-stick-meta":"","header-main-stick-meta":"","header-below-stick-meta":"","astra-migrate-meta-layouts":"default","ast-page-background-enabled":"default","ast-page-background-meta":{"desktop":{"background-color":"var(--ast-global-color-5)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"ast-content-background-meta":{"desktop":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"tablet":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""},"mobile":{"background-color":"var(--ast-global-color-4)","background-image":"","background-repeat":"repeat","background-position":"center center","background-size":"auto","background-attachment":"scroll","background-type":"","background-media":"","overlay-type":"","overlay-color":"","overlay-opacity":"","overlay-gradient":""}},"jir_stock_code":"3133","jir_company_name":"kaihan co.,Ltd.","jir_importance":"\u2605\u2605\u2605\u2605\u2606","jir_publication_date":"2026-11-20","jir_source_link":"https:\/\/japanir.jp\/wp-content\/uploads\/2026\/11\/3133-20261120-06.pdf","jir_short_summary":"In light of financing delays and flood damage in Nepal, the completion timing for Phase 1 of the Nepal hydropower projects has been revised to TBD. Due to continued delays in securing funding and impacts on on-site construction, completion and commercialization timings may be further changed. Phases 2 and 3 are currently under reconsideration.","jir_summary":"### Review of Project Plan and Background\nThe completion schedules for Phase 1 (multiple projects) of the Nepal hydropower projects promoted through consolidated subsidiaries have been reset. Delays in financing and flood damage within Nepal have delayed construction progress, prompting a revision of the model to include adjustments to on-site construction schedules and consideration of rights transfers or project termination. Further changes may occur depending on future financing conditions.\n\n### Outlook and Impact\nCompletion schedules for PJ1\u2013PJ4 remain TBD. For projects from Phase 2 onward, policy decisions are being discussed, including consideration of rights transfers or project termination while taking into account impacts on local operators. Revenue plans and commercialization timing are not confirmed at this time and may be further revised depending on financing and construction progress.","jir_financial_highlights":"Net Sales: Unknown (Unknown)\nPlanned Completion: TBD (TBD)\nFinancing Status: Unknown (Continued delay)","jir_category":"","jir_hashtags":"#kaihan, #DisclosureChange, #NepalHydropower","jir_key_figures":"Current planned completion for PJ1\u2013PJ4: TBD\nPhase 1 interim funding: approx. 100 million yen (Surya's share)\nPhase 1 revenue plan: expected to occur in or after the fiscal year ending March 2027 (19 million yen)","jir_meta_title":"kaihan co.,Ltd. \u2014 Progress Update and Further Revision to Commercialization Timing for Nepal Hydropower Projects | November 2026","jir_meta_description":"kaihan co.,Ltd. has revised the completion timing for Phase 1 of its Nepal hydropower projects to TBD due to financing delays and flood damage. Further changes may occur depending on financing and on-site construction progress.","jir_og_title":"kaihan co.,Ltd. \u2014 Further Revision of Progress for Nepal Hydropower Projects","jir_og_description":"Announcement of a further revision to the progress and commercialization timing of Nepal hydropower projects. Phase 1 completion timing is now TBD against a backdrop of financing delays and flood damage; subsequent impacts will be monitored.","jir_og_image_url":"\/assets\/og\/company-general_ir.jpg","jir_chart_data_collection":"[]","ir_related_company":57441,"ir_release_date":"","ir_type":"","ir_is_new":false,"ir_document_url":"","jir_ir_type":"disclosure_update","footnotes":""},"sector":[],"importance":[],"class_list":["post-155918","ir_release","type-ir_release","status-publish","hentry"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v24.7 - https:\/\/yoast.com\/wordpress\/plugins\/seo\/ -->\n<title>Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing - Japan IR<\/title>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\/\/schema.org\",\"@graph\":[{\"@type\":\"WebPage\",\"@id\":\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/\",\"url\":\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/\",\"name\":\"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing - Japan IR\",\"isPartOf\":{\"@id\":\"https:\/\/japanir.jp\/en\/#website\"},\"datePublished\":\"2026-11-20T09:06:41+00:00\",\"breadcrumb\":{\"@id\":\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/\"]}]},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\/\/japanir.jp\/en\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\/\/japanir.jp\/en\/#website\",\"url\":\"https:\/\/japanir.jp\/en\/\",\"name\":\"Japan IR\",\"description\":\"\",\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\/\/japanir.jp\/en\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing - Japan IR","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/","schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"WebPage","@id":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/","url":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/","name":"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing - Japan IR","isPartOf":{"@id":"https:\/\/japanir.jp\/en\/#website"},"datePublished":"2026-11-20T09:06:41+00:00","breadcrumb":{"@id":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/"]}]},{"@type":"BreadcrumbList","@id":"https:\/\/japanir.jp\/en\/company\/company-3133\/ir\/3133-20261120-06_wp_disclosure_update\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/japanir.jp\/en\/"},{"@type":"ListItem","position":2,"name":"Notice Regarding Progress of Nepal Hydropower Projects by Consolidated Subsidiaries and Further Revision of Expected Commercialization Timing"}]},{"@type":"WebSite","@id":"https:\/\/japanir.jp\/en\/#website","url":"https:\/\/japanir.jp\/en\/","name":"Japan IR","description":"","potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/japanir.jp\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"}]}},"related_company_data":{"id":"57441","title":"KAIHAN CO LTD","ticker":"3133"},"_links":{"self":[{"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/ir-release\/155918","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/ir-release"}],"about":[{"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/types\/ir_release"}],"replies":[{"embeddable":true,"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/comments?post=155918"}],"version-history":[{"count":0,"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/ir-release\/155918\/revisions"}],"wp:attachment":[{"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/media?parent=155918"}],"wp:term":[{"taxonomy":"sector","embeddable":true,"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/sector?post=155918"},{"taxonomy":"importance","embeddable":true,"href":"https:\/\/japanir.jp\/en\/wp-json\/wp\/v2\/importance?post=155918"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}